CCNP Wireless CUWSS 642-732 Summary Notes 24 : Installation Report

Posted on Updated on


Post Deployment

A detailed hardware requirement list should have:

Wireless equipment needed

Supporting infrastructure upgrades

  • RF Validation for the installed wireless network
    • Co channel interference and appropriate channel separation
    • Power levels are consistent with site survey
    • If designing for AP failover or designing to RRM
    • RF Coverage (band by band)
  • Roaming audit
    • Airmagnet can be used in active and also using IPERF
  • Wireless Infrastructure
    • If designing especially globally, verify channel allocation is consistent
    • For 5 GHz band, make sure that the clients support all those UNI bands.Verify that RRM is consistent with what was achieved during survey
  • Application testing
    • Validate all layers 1 through 7

Installation Report / Deliverables

This report describes the deployment methodology and the tests that were performed to validate the installation.

The report should include the following:

  • Spectrum analysis
  • RF coverage analysis
  • Hardware placement and configuration
  • Application analysis – Includes results from application throughput testing

Read the rest of this entry »

CCNP Wireless CUWSS 642-732 Summary Notes 23 : Assessing WLAN Readiness

Posted on Updated on


WLAN Readiness

WCS can be used to assess Wireless coverage readiness for both Location Services and VoWLAN. This however does not replace an onsite post-deployment site survey. The tools used are:

  • Inspect VoWLAN Readiness
  • Inspect location Readiness

Both tools are launched from the map that you are viewing on WCS.  Read the rest of this entry »